Dallas, Texas · Project controls and construction IT since 2021 Projects fail in the forecast, not the field CareersPartnersProgram Rates512-908-5223Data date
Standards & quality · 14 checks

Trust the date after the test.

A finish date is only as good as the network under it. Ours, the contractor’s or yours, every file runs the same fourteen checks, then goes to a second senior reviewer.

The checks

Fourteen ways a schedule lies to you.

Modeled on the DCMA 14-point schedule assessment. Software runs them in minutes. A senior scheduler reads every result and explains it.

LogicCheck 01

Every unfinished activity needs a predecessor and a successor. An open end is work nobody has connected to the finish.

LeadsCheck 02

Negative lags let a task start before its predecessor finishes. They buy time on paper and nowhere else.

LagsCheck 03

Long waits typed into a relationship hide real work, like cure time or review, that should be its own activity.

Relationship typesCheck 04

Finish-to-start ties should carry most of the network. Heavy use of other types makes the path hard to trace.

Hard constraintsCheck 05

Must-finish-on dates override logic. Use enough of them and the schedule reports the date someone wished for.

High floatCheck 06

Months of float on one activity usually means a missing successor, not a lucky cushion.

Negative floatCheck 07

Negative float means the plan already misses a required date. It needs a recovery path, not silence.

High durationCheck 08

Very long activities cannot be measured well. We break them into pieces the field can actually progress.

Invalid datesCheck 09

No forecast dates in the past and no actual dates in the future, measured against the data date.

ResourcesCheck 10

Where the contract calls for loading, activities carry the labor, quantities or cost needed for earned value.

Missed tasksCheck 11

Activities that should have finished by the data date and did not. A rising count is the forecast failing quietly.

Critical path testCheck 12

We add delay to a critical activity. If the finish date does not move by the same amount, the path is broken.

CPLICheck 13

The critical path length index shows whether the remaining path can still make the required finish.

BEICheck 14

The baseline execution index compares tasks finished with tasks planned to finish. It shows whether the plan is being worked.

Frameworks

The methods behind the answer.

Recognized methods and guidance we work to. They are methods, not certifications, and we never present them as anything else.

Critical path method

The foundation under every schedule we build or review: activities, logic, durations and float.

Method

AACE recommended practices

We follow AACE International recommended practices for scheduling, risk analysis and forensic schedule analysis.

Practice guidance

GAO Schedule Assessment Guide

Its best practices for a reliable schedule shape how we score a baseline and write review findings.

Assessment guide

Earned value management

Cost and schedule measured together, so SPI, CPI and the estimate at completion tell one story.

Method
Peer review

Nothing leaves on one signature.

Every baseline, update narrative, risk run and claim exhibit is reviewed by a senior specialist who did not build it, before it reaches the client.

  • Logic and datesThe reviewer reruns the checks and traces the critical path from the data date to the finish.
  • Numbers that tie outCosts, quantities and earned value figures reconcile to the source files.
  • Plain-English narrativeFindings say what moved, why it moved and what the owner should decide.
Data security

Your files stay yours.

Schedules, cost reports and claim files can move markets and disputes. We handle them that way.

01

Need-to-know access

Only the people assigned to your engagement can open your files, and access ends when the work does.

02

Controlled sharing

Files move through the transfer method you approve, never through personal email or public links.

03

Confidential by default

We never name clients or publish project details. Every project on this site is shown as Confidential.

Talk to a scheduler

Put your schedule under load.

Send us an XER or MPP file. We will run the fourteen checks and tell you what they found. A senior project controls lead replies within one business day.