Dallas, Texas · Project controls and construction IT since 2021 Projects fail in the forecast, not the field CareersPartnersProgram Rates512-908-5223Data date
Power & Renewables · U.S. Midwest & Mountain

Onshore Wind Farm Repowering

Eighty-six turbines repowered with new nacelles, blades and controls, finished weeks ahead of the tax credit deadline.

Owner
Confidential
Region
U.S. Midwest & Mountain
Market
Power & Renewables
Capital value
$390M
Size
86 turbines · 300 MW
Delivery
EPC
Duration
18 months
Completed
2024
The challenge

What was at stake.

The tax credit deadline was fixed in law. Crane moves, blade deliveries and wind conditions controlled the pace. The EPC schedule showed one crane path with no allowance for wind days.

Schedule18 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
18 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Crane path planned

Crane moves between turbines were scheduled as real work, with the shortest walking path chosen.

02

Wind days modeled

Historical wind data set the number of lift days per month, so the plan matched the site.

03

Deliveries tracked

Every blade and nacelle shipment was tracked against the turbine it served.

04

Earned value

Turbine-by-turbine earned value showed the owner real progress against the deadline.

Results

The result.

5 weeksAhead of tax credit deadline
$390MCapital controlled
18Months, notice to finish
300 MWRepowered capacity

The deadline was in the tax code. The wind was in the weather records. We put both in the schedule.

Energy scheduler, EvrardBanes
Power & Renewables

Planning something like this?

Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.