Dallas, Texas · Project controls and construction IT since 2021 Projects fail in the forecast, not the field CareersPartnersProgram Rates512-908-5223Data date
Data Centers · U.S. Texas

Multi-Tenant Colocation Data Center

A four-hall, 36 MW colocation data center where every hall was energized and handed to its tenant on the date in the lease.

Owner
Confidential
Region
U.S. Texas
Market
Data Centers
Capital value
$720M
Size
4 data halls · 36 MW
Delivery
CM at-risk
Duration
30 months
Completed
2025
The challenge

What was at stake.

Each data hall was sold to a different tenant with its own ready-for-service date and penalties. Generators, switchgear and chillers had lead times longer than the building itself. The schedule showed construction, but not the commissioning that decided handover.

Schedule30 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Long leads first

Every generator, UPS, switchgear and chiller was tracked from order to set, with float shown against the hall it powered.

02

Commissioning levels

Level one to five commissioning was scheduled hall by hall, ending in integrated systems testing at full load.

03

Tenant milestones

Each lease date became a milestone, reported with float in every update so sales and construction saw the same thing.

04

Earned value

Earned value by hall showed the owner where money and time were going every month.

Results

The result.

4 of 4Halls handed over on lease date
$720MCapital controlled
30Months, ground to last hall
36 MWCritical IT load

In a data center, a late hall is lost revenue for the owner and a broken promise to the tenant. We scheduled to the lease, not to the contractor.

Lola Osoba, Founder, EvrardBanes
Data Centers

Planning something like this?

Send us the project and the date that matters. A senior project controls lead replies within one business day. Building the same kind of project again? Ask about our highly discounted Program Rate.