Regional Medical Center Replacement Hospital

A 320-bed replacement hospital is being scheduled from design to the single day every patient moves from the old building to the new one.

Owner
Confidential
Region
U.S. Texas
Market
Healthcare
Capital value
$980M
Size
690,000 SF · 320 beds
Delivery
CM at-risk
Duration
52 months
Status
In progress · 2027
The challenge

What is at stake.

Design, medical equipment, IT, activation and the patient move each had their own schedule. None of them shared a data date. The owner had already announced the move, and the integrated critical path did not exist yet.

Schedule52 monthsIn progress · finish 2027
20232024202520262027
Today
Start
2023
Planned finish
2027
Time elapsed
75%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

One master schedule

We built an integrated master schedule in Primavera P6 linking design, construction, equipment, IT and activation to the move day.

02

IT as a critical system

Network rooms, nurse call, imaging systems and the electronic health record are scheduled with the same rigor as the mechanical plant.

03

Monte Carlo on move day

Quarterly risk runs give the board P50 and P80 dates for the move, with the top risk drivers named.

04

Dashboards for the board

A Power BI dashboard reads straight from the schedule and cost data, so the board sees one version of the truth each month.

Results

Where it stands.

$980MCapital under control
690K SFReplacement hospital
52Months, design to move day
P80Move date reported quarterly

A hospital move has one day and no second chance. Every schedule on this job now points at that day.

Lola Osoba, Founder, EvrardBanes