K-12 Bond Program: Five New Schools

Five new schools from one voter-approved bond, each opened on the first day of class in the year the district had promised.

Owner
Confidential
Region
U.S. Texas
Market
Education
Capital value
$340M
Size
5 schools · 1 bond program
Delivery
CM at-risk
Duration
32 months
Completed
2023
The challenge

What was at stake.

Five sites, three contractors and one school board that had made a public promise. Each school had its own schedule format and cost report. The board saw five stories every month and could not tell which school was in trouble.

Schedule32 monthsCompleted 2023
202120222023
Start
2021
Finish
2023
Duration
32 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

One program schedule

We rolled five contractor schedules into one program schedule in P6 with a shared calendar and a shared data date.

02

Standard templates

Each school used the same WBS, cost codes and logic library, which made the second through fifth schools faster to control.

03

Bond cash flow

Cash flow forecasts matched bond draws, so the district never borrowed early or ran short.

04

Board reporting

A one-page monthly report showed every school on the same scale, with the real risks named in plain words.

Results

The result.

5 of 5Schools open on the first day
$340MBond program controlled
32Months, first pour to last ribbon
1Program schedule for the board

The second school was easier than the first, and the fifth was the easiest of all. That is what a program is supposed to feel like.

Program controls manager, EvrardBanes