Data Center Substation & Utility Interconnect

A 345 kV substation and utility interconnect that brought 300 MW to a data center campus, scheduled on the same critical path as the buildings.

Owner
Confidential
Region
U.S. Southeast
Market
Data Centers
Capital value
$210M
Size
345 kV · 300 MW
Delivery
EPC
Duration
22 months
Completed
2024
The challenge

What was at stake.

The utility, the owner and the EPC contractor each had a schedule. None of them agreed. Transformers had long lead times, outages on the transmission line had to be booked months ahead, and the campus could not energize without both.

Schedule22 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
22 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Utility work integrated

We built the utility's engineering, outage windows and relay testing into the owner's master schedule as real logic.

02

Transformer tracking

Each power transformer was tracked from factory test through shipping, setting, oil fill and testing.

03

Outage windows locked

Transmission outage requests were planned backward from energization, with the dates confirmed early.

04

Risk weekly

A weekly risk review kept the top ten threats to energization in front of every party.

Results

The result.

On dateCampus energized
$210MCapital controlled
22Months, design to energization
300 MWPower delivered

Most data center delays start at the fence line. We put the substation at the center of the schedule, where it belongs.

Mission critical scheduler, EvrardBanes