Indoor Sports & Aquatic Center

A 220,000 SF indoor sports and aquatic center with a 50 m pool, ready for a championship meet booked before the pool was dug.

Owner
Confidential
Region
U.S. Texas
Market
Sports & Entertainment
Capital value
$135M
Size
220,000 SF · 50 m pool
Delivery
CM at-risk
Duration
26 months
Completed
2024
The challenge

What was at stake.

The pool needed a long cure, fill, heat and water balance before any swimmer could touch it. The contractor schedule gave all of that two weeks. The meet date could not move.

Schedule26 monthsCompleted 2024
202220232024
Start
2022
Finish
2024
Duration
26 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Pool as its own chain

Shell, tile, cure, fill, heating and water chemistry were scheduled with real durations.

02

Meet date as finish

The championship meet became the hard finish, with timing systems and seating sequenced in front of it.

03

Recovery early

When steel slipped, we tested two recovery options and the team chose the one with the most float left.

04

Weekly look-aheads

Three-week look-aheads kept every trade working toward the pool fill date.

Results

The result.

On dateChampionship meet hosted
$135MCapital controlled
26Months, ground to first race
50 mCompetition pool

You cannot rush water chemistry. Once the pool had its real duration, the rest of the schedule had to make room.

Senior scheduler, EvrardBanes