Inpatient Rehabilitation Hospital

An 80-bed inpatient rehabilitation hospital with therapy gyms, aquatic therapy and a training apartment, delivered design-build and opened early.

Owner
Confidential
Region
U.S. Southeast
Market
Healthcare
Capital value
$145M
Size
120,000 SF · 80 beds
Delivery
Design-Build
Duration
30 months
Completed
2025
The challenge

What was at stake.

The design-builder carried design and construction in one schedule with no clear line between them. Early packages were released before design was stable, and the cost model drifted every month without anyone saying why.

Schedule30 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Design packages split

We separated each design package from the work it released, so a late drawing showed up as a late pour weeks ahead.

02

Cost tied to scope

The budget was broken into cost codes matched to the schedule, giving the owner earned value on a design-build job.

03

Float watched monthly

Total float on the therapy wing was tracked monthly and reported in plain words, not just numbers.

04

Early opening tested

When the team saw room to finish early, we tested the compressed plan before anyone promised it.

Results

The result.

3 weeksOpened ahead of plan
$145MCapital controlled
30Months, design to opening
80Beds delivered

We only told the owner it could open early after the schedule proved it. Then it did.

Project controls lead, EvrardBanes
Healthcare