Light Rail Maintenance & Storage Facility

A light rail maintenance and storage facility for 40 vehicles, ready when the first new train arrived from the factory.

Owner
Confidential
Region
U.S. West
Market
Transportation
Capital value
$280M
Size
40-vehicle yard & shop
Delivery
CM/GC
Duration
34 months
Completed
2024
The challenge

What was at stake.

The trains could not be accepted without a yard, a shop, power and signal testing. The facility schedule did not include the systems testing, and vehicle deliveries were already set.

Schedule34 monthsCompleted 2024
202220232024
Start
2022
Finish
2024
Duration
34 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Systems testing added

Traction power, signals and shop equipment testing were added as real chains ending at vehicle acceptance.

02

Vehicle deliveries tracked

Each train delivery was a milestone, and the yard track it needed was scheduled in front of it.

03

CM/GC pricing

We checked each CM/GC work package price against the estimate before the owner agreed to it.

04

Monthly updates

Monthly updates gave the transit board one clear page on schedule and cost.

Results

The result.

On dateYard ready for first train
$280MCapital controlled
34Months, design to acceptance
40Vehicles stored and maintained

The trains were already built. Our job was to make sure they had somewhere to go.

Lead scheduler, EvrardBanes