Transportation · U.S. Southeast

Port Container Terminal Expansion

A 90-acre container terminal expansion with two new berths and ship-to-shore cranes, ready for the shipping lines that had already booked it.

Owner
Confidential
Region
U.S. Southeast
Market
Transportation
Capital value
$610M
Size
90 acres · 2 berths
Delivery
Design-Build
Duration
44 months
Completed
2025
The challenge

What was at stake.

Wharf construction, dredging, yard paving and crane delivery all had to finish in order. The cranes arrived by ship on a fixed date. If the wharf was not ready, the cranes could not be unloaded.

Schedule44 monthsCompleted 2025
2022202320242025
Start
2022
Finish
2025
Duration
44 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Crane arrival as anchor

The crane ship arrival became the anchor milestone, with wharf completion and testing scheduled in front of it.

02

Marine work modeled

Dredging and pile driving carried tide and weather windows in the schedule.

03

Earned value

Quantity-based earned value on piles, deck and paving gave the port an honest progress picture.

04

Claims avoided

Delay events were recorded as they happened, so disputes were settled with facts before they grew.

Results

The result.

On dateBerths ready for first ship
$610MCapital controlled
44Months, marine to operations
90 acresTerminal expansion

A crane ship does not wait for a wharf. We planned the whole terminal around the day it came in.

Senior scheduler, EvrardBanes
Transportation