Central Public Library & Civic Commons

A 140,000 SF central library and civic commons, opened on the morning the city had announced years before.

Owner
Confidential
Region
U.S. Southeast
Market
Government & Civic
Capital value
$96M
Size
140,000 SF
Delivery
CM at-risk
Duration
24 months
Completed
2023
The challenge

What was at stake.

The city announced the opening at groundbreaking. The library had custom shelving, a reading room skylight and a large art program, each with its own long lead time. Nobody had tied them to the opening.

Schedule24 monthsCompleted 2023
202120222023
Start
2021
Finish
2023
Duration
24 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Long leads tied

Skylight glazing, shelving and art installations were scheduled from shop drawings to install, tied to the rooms they served.

02

Collection move planned

Moving the book collection was scheduled as real work in front of the opening, not left to the last week.

03

Change tracked

Design changes from public input were priced and logged, so the council saw their true cost.

04

Plain reporting

A one-page monthly report told the council what changed and why.

Results

The result.

On dateOpening day held
$96MCapital controlled
24Months, ground to opening
140K SFLibrary and commons

A public opening date is a promise from a city to its people. We treated it that way.

Project controls lead, EvrardBanes
Government & Civic