Food & Beverage · U.S. Texas

Beverage Bottling Plant & High-Speed Lines

Four high-speed filling lines in a new bottling plant, producing before the summer demand peak that pays for the year.

Owner
Confidential
Region
U.S. Texas
Market
Food & Beverage
Capital value
$150M
Size
4 filling lines
Delivery
Design-Build
Duration
20 months
Completed
2024
The challenge

What was at stake.

The owner signed supply contracts based on the summer start. The design-builder schedule had commissioning compressed into the last month with no room for line trials. One failed trial would have cost the season.

Schedule20 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
20 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Schedule review

Our health check showed missing logic and hard constraints hiding a negative float path through commissioning.

02

Recovery plan

We rebuilt the commissioning sequence so the first two lines started trials six weeks earlier.

03

Trial time protected

Line trials and quality release were given real durations and protected as a milestone the team could see.

04

Weekly updates

Weekly updates during start-up tracked every line against its own finish.

Results

The result.

On dateLines ready for summer
$150MCapital controlled
20Months, design to first bottle
4High-speed lines commissioned

The old schedule looked fine because its constraints hid the problem. Remove them and the real path showed up in a day.

Schedule analyst, EvrardBanes
Food & Beverage