Frozen Foods Cold Storage Distribution Center

A 310,000 SF freezer distribution center is being scheduled around the slow, controlled pull-down that keeps the floor from heaving.

Owner
Confidential
Region
U.S. Midwest & Mountain
Market
Food & Beverage
Capital value
$185M
Size
310,000 SF freezer
Delivery
Design-Build
Duration
22 months
Status
In progress · 2026
The challenge

What is at stake.

A freezer floor must be brought down to temperature over weeks, and nothing can rush it. The contractor schedule treated the pull-down as a two-day task. Tenants have signed receiving dates that depend on it.

Schedule22 monthsIn progress · finish 2026
20252026
Today
Start
2025
Planned finish
2026
Time elapsed
94%
Our approach

How we control it.

What our schedulers and cost engineers are doing on this project.

01

Pull-down as real work

The temperature pull-down is scheduled as a multi-week chain with its own hold points and readings.

02

Refrigeration critical

Ammonia refrigeration equipment, piping and testing sit on the critical path where they belong.

03

Racking and doors

Racking, dock doors and automation are sequenced so they install before the box goes cold.

04

Tenant dates tracked

Each tenant receiving date is a milestone with float reported in every monthly update.

Results

Where it stands.

$185MCapital under control
310K SFFreezer space
22Months to first receipt
WeeklyPull-down readings tracked

You cannot hurry cold. Once the pull-down was in the schedule at its real length, every other date fell into place.

Senior scheduler, EvrardBanes
Food & Beverage