Lifestyle Retail Center Redevelopment

An 850,000 SF lifestyle retail center rebuilt around stores that stayed open, with the holiday season untouched.

Owner
Confidential
Region
U.S. Midwest & Mountain
Market
Commercial & Mixed-Use
Capital value
$240M
Size
850,000 SF
Delivery
CM at-risk
Duration
30 months
Completed
2025
The challenge

What was at stake.

Tenants could not lose access during the holidays, and every phase moved parking, entrances and utilities. The phasing plan was a drawing. The schedule did not know about the holidays at all.

Schedule30 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
30 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Holidays as blackout

Holiday periods became blackout windows in P6, so no disruptive work could be planned inside them.

02

Tenant access logic

Every store entrance and parking change was tied to the phase that allowed it.

03

Change management

Tenant-driven changes were priced and logged quickly, keeping landlord costs clear.

04

Monthly reporting

A short monthly report showed the owner progress, cost and tenant impacts on one page.

Results

The result.

0Holiday disruptions
$240MCapital controlled
30Months, phase by phase
850K SFRetail center rebuilt

The calendar that mattered most belonged to the stores. We put it in the schedule first.

Lead scheduler, EvrardBanes