Commercial & Mixed-Use · U.S. Texas

Suburban Logistics Park

Five logistics buildings totaling 2.4 million SF, turned over to tenants in the order their leases required.

Owner
Confidential
Region
U.S. Texas
Market
Commercial & Mixed-Use
Capital value
$310M
Size
5 buildings · 2,400,000 SF
Delivery
Design-Build
Duration
20 months
Completed
2023
The challenge

What was at stake.

Tenants signed leases on fixed dates, but the contractor scheduled the buildings in the order easiest to build. Two tenants would have been late. Nobody had compared the schedule to the leases.

Schedule20 monthsCompleted 2023
20222023
Start
2022
Finish
2023
Duration
20 mo
Our approach

How we controlled it.

What our schedulers and cost engineers did on this project.

01

Leases into the schedule

Each lease turnover date became a milestone, and we resequenced the buildings to meet them.

02

Tilt-wall rhythm

Panel casting and erection moved from building to building in a steady rhythm the crews could follow.

03

Cost by building

Costs were tracked by building, so the owner knew the real cost of each lease.

04

Weekly updates

Weekly updates during turnover kept tenant improvement work in sync.

Results

The result.

5 of 5Buildings turned over on lease
$310MCapital controlled
20Months across five buildings
2.4M SFLogistics space

The fix was simple once someone put the leases next to the schedule. That someone should always be on the owner's side.

Project controls lead, EvrardBanes
Commercial & Mixed-Use